The existing basement of this property in Ewhurst, Surrey varied in depth from 0 to 2.20m.

The existing footings were underpinned to depths of up to 4m and approximately
300 m³ of spoil was removed to provide an overall basement depth of 3.50 metres. We then constructed a new slab, which was tied into new underpinning bays.

All access was through the small doorway shown.

The whole basement was subsequently lined with damp proofing.